A serial-number-led handover checklist created after comparing retained 40T-300T commissioning files. It replaces ambiguous archive shorthand with the evidence a qualified electrician needs to record: supply, rated current, protection, conductor design basis, protective earth, phase sequence, isolation and authorisation. It is a record structure, not an electrical design or permission to energize.

Hydraulic press brake electrical supplyZWCNC archive review, 31 August 2026Pre-energization evidence checklist

What this reference covers

  1. 1Machine model, serial plate and matching electrical drawing revision
  2. 2Supply voltage, phases, frequency, rated current and installed options
  3. 3Protective-device and conductor design basis with responsible person
  4. 4Protective-earth path, continuity/measurement record and instrument ID
  5. 5Isolation status, phase-sequence plan, enclosure closure and energization authority

Field verification checklist

Use only the electrical drawing and ratings for the delivered serial number
Record the qualified electrician and the applicable site standard or authority
Document upstream isolation and verify absence of hazardous energy before connection work
Record conductor material, cross-section, route, run length, protection and calculation basis rather than copying an archive number
Define first-energization stop conditions and capture results without bypassing guards or interlocks