A controlled commissioning handover for foundation support, worktable leveling, reservoir identity, approved oil, cleanliness, fill indication and post-start observations. It preserves the useful common structure found across seven retained procedures while preventing their approximate preparation quantities from being treated as universal fill volumes.

40T-300T hydraulic press brakesZWCNC archive review, 31 August 2026Mechanical and hydraulic handover checklist

What this reference covers

  1. 1Foundation, support-plate and anchoring inputs from the machine plan
  2. 2Level instrument, calibration status, measurement positions and results
  3. 3Reservoir identity, approved oil grade, supplier batch and cleanliness controls
  4. 4Actual fill indication and retained quantity record without assuming the archive estimate
  5. 5Leak, temperature, noise, pressure and axis observations after authorised startup

Field verification checklist

Confirm the foundation and support arrangement for the delivered machine rather than assuming the archive plate example
Record the calibrated level, measurement locations, readings and acceptance limits
Verify oil grade and cleanliness from the machine hydraulic documentation and supplier record
Fill to the machine-specific indicator and record actual quantity; do not use the archive estimate as a stop point
After authorised startup, record leaks, temperature, abnormal noise and axis behaviour before handover