ZWCNC TECHNICAL ARCHIVE

100T3200 Press Brake Installation and Commissioning Process

A retained ZWCNC field procedure for preparing hydraulic oil, electrical cable and levelling pads, then levelling the machine, filling the tank, connecting power and preparing the first controlled start.

100T3200 hydraulic press brakeRetained factory procedureZWCNC commissioning record

What this reference covers

  1. 1Site consumables and levelling-pad preparation
  2. 2Machine levelling sequence
  3. 3Hydraulic-oil filling location and level check
  4. 4Power and protective-earth connection
  5. 5Foot switch and first-start preparation

Field verification checklist

Treat listed cable and oil quantities as record-specific, not universal specifications
Match supply voltage and conductor sizing to the actual machine nameplate and local code
Have a qualified electrician verify protective earth and phase sequence
Keep the emergency stop available during first motor-direction checks
Complete the machine-specific acceptance sheet before production